Delphi
News and Activities during the 1999/2000 shutdown.

If you have information you think might be useful to be put on this page (or find anything wrong), please let me know: Andre.Augustinus@cern.ch or 163534

oSince the shutdown is nearing its end, I will from now on update this page only occasionally.
Sorry about that, but I hope you enjoyed this page...

 

oLatest News

(updated 29-mar 2000 at 13:00)
o First beam circulated in LEP on the early morning of 29-mar. First collisions can be expected as early as monday 3-apr.
o Pit meetings will now be held according to the usual schedule: monday, wednesday, friday; usual time, usual place (16:00 in the pit meeting room).
The minutes of the last pit meetings are available at the usual place.
back to top
 

oRecommendations to detectors

o The start of the 2000 data taking campaign is near. So this might be a good time to do a spring cleaning of your SX8 and UX8 locations, to keep there only the necessary stuff for efficient working.
o Philippe Gavillet has started to update the Pit8 Phone List for 2000. Please have a look and mail Philippe any modifications.
o The fix of a Y2K bug in the database access package requires that all programs that access the databases to be relinked. This concerns in particular Elementary Processes (the 'official' version 4.A/2 has already be relinked), see also this news posted by Tim.
o In case your GSM telephone was suspended during the shutdown, please check if it works again. If not, contact Philippe Charpentier.
back to top
 

oActual situation of Delphi

(updated 29-mar 2000 at 13:00)
o Gas is stable for all detectors. The flammable gas zone has officially been re-installed 6-mar, and SLIMOS shifts have started. Cosmics datataking has started 14 mar. Solenoid is running nominal. The RIB has been heated up to 40 degr. C.
o Delphi (as wel as most of the rest of the world) survived the jump into the year 2000.
It also survived the two heavy storms, with only minor damage (damaged air extraction pipes, unforeseen interruptions of the online cluster).
back to top
 

oOverview of Activities

(updated 17-mar 2000 at 12:30)
o Power Cuts
 
23 nov 1999 (7:00 - 13:30) Annual AU (Arrets d'Urgence) test (ST-NC-EL-99-041)
13 dec 1999 (7:30 - 16:30) Transformer maintenance (SF, SE, SX, SR).
Two 2 min. cuts at 8:00 and 16:00.
(ST-NC-EL-99-046)
29 feb 1999 Alarm 3 tests (smoke tests).
  o Delphi
08 nov 1999 - 11 nov 1999 Gas purge.
15 nov 1999 - 16 dec 1999 End Cap A open. Detailed planning
during opening.
15 nov 1999 - 19 jan 2000 End Cap C open.
14 dec 1999 Morning: shutdown and reboot online and cluster.
18 dec 1999 - 03 jan 2000 Limited online and offline cluster. (details)
31 jan 2000 - 11 feb 2000 Solenoid maintenance (warm).
14 feb 2000 - 28 feb 2000 Gas system maintenance.
24 feb 2000 - 05 mar 2000 Solenoid cooldown.
04 mar 2000 Delphi cryogenics ready.
06 mar 2000 Start of gas and shifts.
10 mar 2000 - 14 mar 2000 Solenoid maintenance (cold); leave field on.
  o LEP dates               draft LEP schedule for 2000.
03 mar 2000 - 13 mar 2000 SC quads cooldown and power tests.
16 mar 2000 LEP closure.
01 apr 2000 LEP startup.
05 apr 2000 LEP physics (Z0).
10 apr 2000 LEP physics (High Energy).
  o Safety
15 nov 1999 - 11 feb 2000 SDN and fire detection maintenance.
18 nov 1999 - 19 nov 1999 Evacuation alarm tests.
29 nov 1999 - 17 dec 1999 DEF & VESDA maintenance.
07 feb 2000 - 25 feb 2000 Maintenance & L3 alarm tests on IMS detection (SG only).
07 feb 2000 - 28 feb 2000 Maintenance & L3 alarm tests on IGD detection (SG and UX).
  o Infrastructure
16 nov 1999 - 16 feb 2000 Cryogenics stopped.
10 dec 1999 - 07 feb 2000 Cooling water maintenance. See also "Notes de Coupure"
13 dec 1999 - 17 dec 1999 Ventilation maintenance UX.
17 dec 1999 EDF network off (but backup from swiss network),
in principle no power interruption.
16 feb 2000 - 04 mar 2000 Cryogenics startup.
21 feb 2000 - 25 feb 2000 Ventilation maintenance SG (stop 24 feb 13:30 - 17:00).
  o Miscellaneous
16 dec 1999 - 03 jan 2000 Computer Center shutdown schedule
04 mar 2000 "mini open day" school classes and students only. No other visits allowed.
  o Overview
Click on the planning to get a detailed view
back to top
 

oDetailed Calendar

week date activity
45 08-nov
14-nov
08: calibration HPC, TPC, ...
08: start gas purge
11: end gas purge
11: (18:00) last shifts
12: flammable gas zone lifted
46 15-nov
21-nov
15: opening EndCap A
15: opening EndCap C
15: start SDN and fire detection maintenance
16: stop of cryogenics
47 22-nov
28-nov
23: Annual AU (Arrets d'Urgence) test (7:00-13:30)
48 29-nov
05-dec
29: start DEF & VESDA maintenance
49 06-dec
12-dec
08: (14:00) 1999 Running Review Workshop
08: (18:00) End of the Year party
10: start cooling water maintenance
50 13-dec
19-dec
13: Transformer maintenance (SF,SE,SX,SR) (7:30-16:30)
(two 2 min. cuts at 8:00 and 16:00)
13: start ventilation maintenance UX
13: closing EndCaps (C postponed to mid-january)
14: morning, cluster stop and reboot
(UPS battery replacement, smoke tests)
16: Close EndCap A
17: EDF network off (but backup from swiss network)
17: end ventilation maintenance UX
17: end DEF & VESDA maintenance
51 20-dec
26-dec
Christmas Closure
52 27-dec
02-jan
Christmas Closure
01 03-jan
09-jan
 
02 10-jan
16-jan
 
03 17-jan
23-jan
19: closing EndCap C
22-23: power cuts Meyrin site
04 24-jan
30-jan
Delphi Week
05 31-jan
06-feb
31: begin of EDF network off, swiss network will take over
(no power interruption foreseen)
31: start warm solenoid maintenance
06: EDF network back on
06 07-feb
13-feb
07: end cooling water maintenance
07: start IGD (SG & UX) and IMS (SG only) maintenance and L3 tests
(No power interruption foreseen)
11: end SDN and fire detection maintenance
11: end warm solenoid maintenance
07 14-feb
20-feb
14: start gas maintenance
08 21-feb
27-feb
Delphi Analysis Week
21: start ventilation maintenance SG
24: ventilation stop SG
24: start solenoid cooldown
25: end IMS maintenance SG
25: end ventilation maintenance SG
09 28-feb
05-mar
28: end IGD maintenance SG & UX
28: end gas maintenance
29: alarm 3 tests (smoke tests)
03: start cooldown SC quads
04: mini open day, no other visits allowed
04: DELPHI cryogenics ready
05: solenoid cooled down
10 06-mar
12-mar
06: Start of gas and shifts
10: start cold solenoid maintenance
12: SC quads cooled down
11 13-mar
19-mar
14: end cold solenoid maintenance
14: Start cosmics datataking
16: LEP closure
12 20-mar
26-mar
 
13 27-mar
02-apr
01: End of cosmics datataking
01: LEP startup
14 03-apr
09-apr
05: LEP physics (Z0)
15 10-apr
16-apr
Delphi Analysis Week
10: LEP physics (High Energy)