| Latest News | Recommendations to detectors | Actual situation of Delphi |
| Overview of Activities | Detailed Calendar | "Notes de Coupure" |
![]() last update 29-mar 2000 at 13:00 (history) |
Delphi
|
| If you have information you think might be useful to be put on this page (or find anything wrong), please let me know: Andre.Augustinus@cern.ch or 163534 |
Since the shutdown is nearing its end, I will from now on
update this page only occasionally.
Latest News| (updated 29-mar 2000 at 13:00) | |
| First beam circulated in LEP on the early morning of 29-mar. First collisions can be expected as early as monday 3-apr. |
|
Pit meetings will now be held according to the usual schedule: monday, wednesday, friday; usual time, usual place
(16:00 in the pit meeting room). The minutes of the last pit meetings are available at the usual place. |
Recommendations to detectors
| The start of the 2000 data taking campaign is near. So this might be a good time to do a spring cleaning of your SX8 and UX8 locations, to keep there only the necessary stuff for efficient working. |
| Philippe Gavillet has started to update the Pit8 Phone List for 2000. Please have a look and mail Philippe any modifications. |
| The fix of a Y2K bug in the database access package requires that all programs that access the databases to be relinked. This concerns in particular Elementary Processes (the 'official' version 4.A/2 has already be relinked), see also this news posted by Tim. |
| In case your GSM telephone was suspended during the shutdown, please check if it works again. If not, contact Philippe Charpentier. |
Actual situation of Delphi| (updated 29-mar 2000 at 13:00) | |
| Gas is stable for all detectors. The flammable gas zone has officially been re-installed 6-mar, and SLIMOS shifts have started. Cosmics datataking has started 14 mar. Solenoid is running nominal. The RIB has been heated up to 40 degr. C. |
|
Delphi (as wel as most of the rest of the world) survived the jump into the year 2000. It also survived the two heavy storms, with only minor damage (damaged air extraction pipes, unforeseen interruptions of the online cluster). |
Overview of Activities| (updated 17-mar 2000 at 12:30) | |||||||||||||||||||||||||
| Power Cuts | ||||||||||||||||||||||||
| |||||||||||||||||||||||||
|
Delphi
| ||||||||||||||||||||||||
|
LEP dates
draft LEP schedule for 2000.
| ||||||||||||||||||||||||
|
Safety
| ||||||||||||||||||||||||
|
Infrastructure
| ||||||||||||||||||||||||
|
Miscellaneous
| ||||||||||||||||||||||||
| Overview | ||||||||||||||||||||||||
Detailed Calendar| week | date | activity |
|---|---|---|
| 45 | 08-nov 14-nov | 08: calibration HPC, TPC, ... 08: start gas purge 11: end gas purge 11: (18:00) last shifts 12: flammable gas zone lifted |
| 46 | 15-nov 21-nov | 15: opening EndCap A 15: opening EndCap C 15: start SDN and fire detection maintenance 16: stop of cryogenics |
| 47 | 22-nov 28-nov |
23: Annual AU (Arrets d'Urgence) test (7:00-13:30) |
| 48 | 29-nov 05-dec | 29: start DEF & VESDA maintenance |
| 49 | 06-dec 12-dec | 08: (14:00) 1999 Running Review Workshop 08: (18:00) End of the Year party 10: start cooling water maintenance |
| 50 | 13-dec 19-dec |
13: Transformer maintenance (SF,SE,SX,SR) (7:30-16:30) (two 2 min. cuts at 8:00 and 16:00) 13: start ventilation maintenance UX 13: closing EndCaps (C postponed to mid-january) 14: morning, cluster stop and reboot (UPS battery replacement, smoke tests) 16: Close EndCap A 17: EDF network off (but backup from swiss network) 17: end ventilation maintenance UX 17: end DEF & VESDA maintenance |
| 51 | 20-dec 26-dec | Christmas Closure |
| 52 | 27-dec 02-jan | Christmas Closure |
| 01 | 03-jan 09-jan | |
| 02 | 10-jan 16-jan | |
| 03 | 17-jan 23-jan | 19: closing EndCap C 22-23: power cuts Meyrin site |
| 04 | 24-jan 30-jan | Delphi Week |
| 05 | 31-jan 06-feb | 31: begin of EDF network off, swiss network will take over (no power interruption foreseen) 31: start warm solenoid maintenance 06: EDF network back on |
| 06 | 07-feb 13-feb | 07: end cooling water maintenance 07: start IGD (SG & UX) and IMS (SG only) maintenance and L3 tests (No power interruption foreseen) 11: end SDN and fire detection maintenance 11: end warm solenoid maintenance |
| 07 | 14-feb 20-feb | 14: start gas maintenance |
| 08 | 21-feb 27-feb | Delphi Analysis Week 21: start ventilation maintenance SG 24: ventilation stop SG 24: start solenoid cooldown 25: end IMS maintenance SG 25: end ventilation maintenance SG |
| 09 | 28-feb 05-mar | 28: end IGD maintenance SG & UX 28: end gas maintenance 29: alarm 3 tests (smoke tests) 03: start cooldown SC quads 04: mini open day, no other visits allowed 04: DELPHI cryogenics ready 05: solenoid cooled down |
| 10 | 06-mar 12-mar | 06: Start of gas and shifts 10: start cold solenoid maintenance 12: SC quads cooled down |
| 11 | 13-mar 19-mar | 14: end cold solenoid maintenance 14: Start cosmics datataking 16: LEP closure |
| 12 | 20-mar 26-mar | |
| 13 | 27-mar 02-apr | 01: End of cosmics datataking 01: LEP startup |
| 14 | 03-apr 09-apr | 05: LEP physics (Z0) |
| 15 | 10-apr 16-apr | Delphi Analysis Week 10: LEP physics (High Energy) |